The permit is on your critical path whether you plan for it or not. We handle it in both states, and we schedule around your build sequence.
For builders, the septic permit is what gates the building permit, and in Georgia it comes with a twelve month expiry and a mandatory county inspection before backfill. We file in both states, coordinate the soil evaluation, and time permits against the build sequence so they neither expire early nor arrive late. We are Tier 3 in South Carolina, so a lot that fails a conventional soil evaluation does not become a stalled lot.
SCDES ePermitting in South Carolina, county Board of Health in Georgia. Different systems, different rules, both ours.
Georgia permits expire after twelve months. On a phased release, pulled too early means pulling them twice. We time them against your sequence.
A denied soil evaluation is not a dead lot, it is an engineered design. Only a Tier 3 installer can legally install one in South Carolina, and we hold that licence.
Georgia inspects before backfill on every job. We book it rather than hoping. On the South Carolina side our Tier 3 licence lets us self-inspect, which usually saves a week.
Across a subdivision, one point of contact and one schedule rather than a permit conversation per lot.
Tank capacity follows bedroom count. Change the plan and we adjust the design rather than discovering it at inspection.
Georgia construction permits are valid twelve months. South Carolina gives you five years. On a phased development in Columbia County, permits pulled at the start of a two year build will expire before the houses exist. This is the single most common avoidable delay we see.
Georgia requires a County Board of Health inspection before the system is covered, without exception. It happens, and uncovering a finished system is a bad day for everyone. It goes in the schedule.
We will tell you what the lots will take, what the permits will need, and how long it realistically takes.